Selected EPCM Malaysia references, from site due diligence and planning review to coordinated engineering design and delivery.

JHB3 data centre concept campus rendering

Johor Bahru

JHB3 Data Center

Technical due diligence

Site review for a 10-hectare plot, including planning controls, legal restrictions, permitting overview and utility review.

  • Planning control review
  • Site utility review
  • Client listed as Australian DC Company

Started November 2024 · completed

JHB2 data centre concept rendering

Johor Bahru

JHB2 Data Center

Technical due diligence gap assessment

Site review for a 10-hectare plot, including planning controls, legal restrictions, permitting overview and utility review.

  • Planning control review
  • Site utility review
  • Client listed as Australian DC Company

Started September 2024 · completed

JHB1 data centre concept rendering

Johor Bahru

JHB1 Data Center

Site due diligence · desktop review

Desktop review of planning controls, legal restrictions, permitting and site utilities for a 10-hectare Johor site.

  • Desktop due diligence review

October–November 2023

KUL data centre concept rendering

TPM · Cyberjaya · Nilai

KUL 070 / 071 / 072

Due diligence for three sites

Site due diligence to identify issues that could affect acquisition, development and later data-centre operations.

  • 2-storey test fit
  • Additional multistorey test fit
  • Client listed as US DC Company

April–September 2022

GPR data centre campus concept rendering in Selangor

Selangor

GPR1A / 2A / 3A Data Center

Architectural and engineering services

Large-scale data-centre development on an estimated 146.85-acre site, with capacity planned to scale in phases.

  • 146.85 acres
  • 34.8 MW Day 1 IT load
  • Up to 217.5 MW non-densified
  • Up to 480 MW densified
  • Client listed as US DC Company

Started June 2025 · ongoing in supplied pack

SCF1A data centre concept rendering in Selangor

Selangor

SCF1A Data Center

Architectural and engineering services

Two-phase data-centre development on an estimated 58-acre site.

  • 58 acres
  • 34.8 MWc Phase 1
  • 72.534 MWc Phase 2
  • Tier III
  • Client listed as US DC Company

December 2024–March 2025

K Valley data centre concept rendering in Cyberjaya

Cyberjaya

K Valley Data Center

Engineering design · CSA and MEP

Four-storey, two-phase data centre with BIM coordination, clash analysis, CFD and M&E fit-out.

  • 4.5–5 acres
  • 9.2 MW total IT load
  • Tier III
  • PUE targets: 1.45 enterprise · 1.4 wholesale

April 2024–February 2026